Check the installed equipment against the approved drawing.
Witness the acceptance test performed by the installing contractor.
Check for proper jockey pump operation.
The auto run time for the fire pump shall be set at 10 Minutes.
A roof shot from one standpipe shall be performed.
Verify that all pertinent information such as on/off pressures, dispatch phone number, and alarm position number are labeled at the pump control box.
Rest all controls to normal; verify with dispatch that the proper signals where received.
A copy of the test results shall be forwarded to the Fire Prevention office.
Search results
Website Accessibility Statement
Fort Lupton Fire Protection District (the "District") is committed to ensuring that its services are accessible to all
members of the public. As part of this commitment, the District strives to provide an accessible website compatible with
the Web Content Accessibility Guidelines (WCAG) version 2.1, AA, and commercial screen reading software. Features of the
website are created to allow individuals with vision and other impairments to understand and use the website to the same
degree as someone without disabilities.