Fire Pump Test

  1. Check the installed equipment against the approved drawing.
  2. Witness the acceptance test performed by the installing contractor.
  3. Check for proper jockey pump operation.
  4. The auto run time for the fire pump shall be set at 10 Minutes.
  5. A roof shot from one standpipe shall be performed.
  6. Verify that all pertinent information such as on/off pressures, dispatch phone number, and alarm position number are labeled at the pump control box.
  7. Rest all controls to normal; verify with dispatch that the proper signals where received.
  8. A copy of the test results shall be forwarded to the Fire Prevention office.